|
Terminating
the Sale
Purchase
Agreement
before
the
performance
date -
is there
a law of
anticipatory
breach
in UAE? |
|
|
|
TLG victorious in procuring
judgment against a defaulting
developer before the performance
date. |
| |
|
The recent wave of global
financial crisis paralyzed the
Dubai property and construction
market after enjoying almost a
six year period of rapid boom.
With many construction sites
left abandoned or breathing only
minimal progress, the suspense
mounts for an ardent investor
thinning its confidence in to a
trickle albeit the sale and
purchase agreement stipulates a
time period which is yet to
expire. Eventually the investor
is dawned with the possibility
of never receiving possession of
his property on the date
expressly and mutually agreed
between both parties. While a
delay in construction is
aggravating in itself, the
question is whether an aggrieved
purchaser can ask for a
termination of the contract
before the performance is due? |
| |
|
The doctrine of anticipatory
breach |
| |
|
There may come a time when one
party to the contract expresses
the unwillingness to perform its
obligations under the contract.
Owing to the bilateral and
reciprocal nature of a contract,
the innocent party may be
severely prejudiced and burdened
with the obligations under a
contractdue to intention of
non-performance by the other
party. Hence instead of waiting
for the time period to expire,
the other party may terminate
the contract before the
performance is due to mitigate
its losses.
The above scenario is addressed
by the common law principle of
anticipatory breach which was
first established in the case of
Hochester v De la Tourdating
back to 1853. According to the
doctrine of anticipatory breach,
an aggrieved party can ask for
the termination of the contract
before the time for its
performance has arrived provided
the ingredients of a repudiatory
breach are present. The
fundamental element in
establishing an anticipatory
breach is the communication of
an expressed statement from the
promisor that he does not intend
to perform his obligation under
the contract.
In a recent decision, SK
Shipping (S) Pte Ltd v
Petroexport Ltd [2009], the UK
Commercial Court provided
additional guidance as to when
the innocent party can claim
that there has been renunciation
and/oranticipatory breach. To
establish the intention of the
defaulting party, it is enough
that the party acted in such a
way so as to evince a clear and
absolute intention that it would
not perform its obligations, and
that the words or conduct of the
party would be clear and
absolute intention that it would
not perform its obligations,
that the words or conduct of the
party would be clear and
absolute to a reasonable person
taking into consideration all
circumstances at the time of
termination. In addition to
this, in order to terminate the
contract, the innocent party
must subjectively belief that
the other party will fail to
honor its contractual
obligations in order to
terminate the contract.
Based on the above, it is
arguable that a delay in
construction of a property by a
developer may constitute as
clear, unequivocal and absolute
intention of the developer to
not to complete the property in
the given time period; hence
establishing the necessary
constituents for anticipatory
breach.
While,the contract law is
governed by the Civil Code in
UAE which is influenced more by
the Civil Code Napoleon along
with Sharia law filling the gaps
and serving as the basis of
authority, the question of the
presence of an equivalent
doctrine remains a moot point.
In sharp contrast, Article 1186
of the French Civil Code
expressly provides that the
performance of an obligation to
be due on a certain event or
stipulated date cannot be
claimed before the occurrence of
such time period. Similarly,
according to Sharia law,
termination can only be granted
when there is real or actual
breach. In this sense, the
incidenceof the breach is most
essential requirement for the
availability of the remedy of
termination. Strictly speaking,
an anticipatory breach does not
constitute an actual breach but
only an anticipation that the
promisor will not live up to the
contractual terms whereby
granting the innocent party an
accelerated remedy to mitigate
its losses.
Article 272(1) of the UAE Civil
Code provides that: ‘In
contracts binding upon both
parties, if one of the parties
does not do what he is obliged
to do under the contract, the
other party may, after giving
notice to the obligor, require
that the contract be performed
or cancelled.'
The Article expressly grants the
remedy of termination in view of
the default of either party to
the contract; however, it does
not elucidate whether such
termination can be granted
before the performance of the
obligation is due.Nonetheless,
deriving its roots inIslamic law
which is based onprinciples of
equitability, such a remedy
should not be considered
impossible in UAE law. |
| |
|
TLG victorious in procuring
termination of contract from the
court before the completion date |
| |
|
In a recent bold and sweeping
ruling from the Dubai Court of
Appeal, the judge established
that a contract for a sale and
purchase of a property can be
terminated before the completion
date resulting from developer’s
breach of its obligation of not
achieving the requisite
milestones of construction. The
Claimant was an investor in a
property in Dubai to be
constructed by the Defendant
latest by 2 April 2011. The
Defendant reserved the right to
extend the completion date not
more than 12 months. Hence the
date of completion was
effectively set at April 2012.
In January 2011, the Claimant
visited the construction site
and noticed that only 13%
percent of the construction had
been achieved proving a very
minimal and indolent progress by
the Defendant.
TLG argued that even though the
defendant had effectively
extended the date to April 2012
and still had time to complete
the property, the level of
progress and consequentially the
delay in construction
constituted a breach in itself
in terms of the stage of
development that ought to have
been achieved by such time.
The judge, in its remarkable
judgment concluded that the
developer did not have any
reasonable reason to justify the
delay and the slow construction
of the property; and since the
Claimant had been duly making
payments according to the
payment plan corresponding the
estimated levels of development,
the developer stood in breach of
its obligation for carrying out
the construction in a delayed
manner.
It is interesting to see that
the in delivering this judgment,
the judge has hinted on the
possibility of operation of
anticipatory breach in UAE
contract law or a species of the
same doctrine. Altogether, it is
worth applauding that the Dubai
courts are not shy to exercise
creative and teleological
interpretation of the civil code
and the Islamic law, setting up
a new dynamics in the contract
law in wake of the modern
economic needs of the society. |
| |
|
A unique decision |
| |
|
A word of caution, even though
the judgment reflects similarity
with the doctrine of
anticipatory breach, the ruling
is one of its kind and unique in
its disposition. The fact that
the completion of the property
was only 13% by January 2011
meant that the construction of
the unit was not possible even
on the extended completion date
of April 2012, thus effectively
establishing the required
intention of the Defendant that
they will not honor their
obligations under the contract.
However, the Judge was careful
in stating that the act of
Defendant not completing the
required level of construction
in a timely manner stands as an
actual breach of the contract.
This leads to the conclusion
that under a sale and purchase
agreement to develop a property,
the developer has levels and
stages of obligations rather
than the wholesome duty of
completing the property in the
agreed time. The court has
hereby set a stringent test of
performance in a contract to
construct a property.This is
also reflected in Dubai Law No.8
of 2007 (the “Escrow Law”)
whereby the payments made by the
Purchaser should be linked with
the construction levels.
Provided that the purchaser duly
made payments according to the
payment plan, it is the duty of
the developer to utilize the
monies received solely for the
purpose of developing the
relevant real estate project.The
fact that the payments made by
the Claimant did not match the
required construction milestone
meant that the Defendant had
defaulted in its obligations
constituting a material breach
of the contract.This is a
favorable and welcomed
interpretation of the law in
light of the new property law
and regulations, and a step
towards strengthening and
complementing the same. Amidst
the pressures of an ailing real
estate market, UAE is resolute
in protecting investors and
ensuring smooth development in
the Emirate.
While the judgment sheds light
on the likelihood of a
defaulting party standing in
breach of a contract before the
date of performance is due, the
existence and scope of the
doctrine of anticipatory breach
in UAE law is left open for
speculation and debate. |
| |
July
2011
© The Legal Group |
|
|
 |
|
 |
|
|
|
Shadha
Zawawi
Associate |
|
Dubai,
UAE
Tel:
+971 4
4477044
Fax:
+971 4
4477088
Email:
Shadha.zawawi@tlg.ae |
|
|
|
|
|