|
Force
Majeure:
An
Excuse
Misunderstood
in the
UAE |
|
|
|
After the crash of the UAE real
estate market a large majority
of real estate project
developers who were planning to
construct iconic projects and
anticipating large investment
returns had to re-consider their
decisions. But this exposed them
to another wrath, this one from
investors who paid them large
sums of money when the market
was different.
I have seen a plethora of
articles, including one of my
own, on the origin, scope and
meanings of force majeure. In
this article I am putting
forward what the legal position
and liability of a developer
would be if a force majeure
event indeed occurs and is
proven in court. By the end of
this article it will become
apparent that force majeure is
not a golden shield protecting a
developer from all monetary
obligations and, therefore, not
what the developer hopes it to
be.
A force majeure event excuses
the developer from the
performance of its obligations
under the agreement and exempts
the developer from the
contractual and legal
liabilities it would otherwise
be exposed to for breach of the
performance of these
obligations. |
| |
| Therefore, two preliminary
questions must be addressed: |
| |
-
What was the contractual
obligation of the developer?
To construct a project and
hand it over to the
respective purchasers within
a pre-defined, specified and
agreed time period.
-
What is the contractual and
liability of the developer
if performance obligation is
breached?
Article 272 of the UAE Civil
code states that
(1) In contracts binding on
both parties, if one of the
parties does not do what he
is obliged to do under the
contract, the other party
may … require that the
contract be performed or
cancelled.
(2) The judge may order the
obligor to perform the
contract forthwith or may
defer (performance) to a
specified time, and he may
also order that the contract
be cancelled and
compensation paid in any
case if appropriate.
|
| |
|
Suppose I purchased a property
in 2004 for AED 1,000,000.00 and
the obligation of the developer
was to hand over the property in
2006. In 2006, the value of this
property is AED 4,000,000.00 but
the developer has not
constructed the property or has
failed to hand it over to me. |
| |
-
If performance is still
possible and the court
orders performance
forthright, I will get the
property worth AED
4,000,000.00.
-
If court delays performance,
I will get the property and
given such compensation
which will put an X in the
box as if the contract had
been performed.
-
If performance cannot
occur (because of a reason
besides force majeure) the
judge will order
cancellation of the
agreement and give me only
compensation.
|
| |
|
The aim of this compensation is
to put me in a position in which
I would have been had the
contract been performed
according to its terms. If the
damages were calculated by only
refunding what I have paid under
the agreement, then the
developers in a rising market
may purposely fail to hand over
and upon cancellation refund me
my AED 1,000,000.00 and sell my
property for AED 4,000,000.00,
the market value in 2006.
Therefore, compensation for
breach or cancellation of an
agreement is calculated to
protect the expectation
interest.
Now suppose that the developer
did not hand over the property
because a force majeure event
occurred. What would I be
entitled to then?
A force majeure event excuses
the effected party from
continuing to perform its
obligation. Therefore, I cannot
compel the developer to continue
the construction; I cannot
compel the developer to hand
over the unit; and I cannot
compel the developer to give me
compensation and damages because
the occurrence of force majeure
event does not make him liable
for any breach of the
obligations.
But that does not prevent the
cancellation of the agreement.
The force majeure excuse does
not exonerate the developer from
not refunding the money which
was paid by me for the
performance of its obligation.
Therefore, whilst the developer
will not perform the obligation
and I cannot seek specific
performance of the agreement, I
will be entitled to a refund of
the amount I paid towards the
now unable/impossible to be
performed agreement. In fact,
the very effect of the
occurrence of a force majeure
event is the automatic
cancellation of the agreement;
this is the simple and clear
application of Article 273 of
the UAE Civil Code: |
| |
-
In contracts binding on both
parties, if force majeure
supervenes which makes the
performance of the contract
impossible, the
corresponding obligation
shall cease, and the
contract shall be
automatically cancelled.
|
| |
| Article 274 |
| |
-
If the contract is cancelled
automatically or by the act
of the parties, the two
contracting parties shall be
restored to the position
they were in before the
contract was made…
|
| |
|
Therefore, the developer will
refund me only the AED
1,000,000.00 as opposed to
giving me compensation that
would put me in a position in
which I would be if the
agreement was performed. I will
be paid AED 1,000,000.00 and
sent home.
The same principle is upheld by
the English Law Reform
(Frustrated Contracts) Act 1943.
As per s.1(2) of this Act,
moneys paid prior to the
frustrating event are
recoverable; money which was
payable prior to the time of
performance ceases to be
payable.
But what is ironic is that most
purchasers in my hypothetical
situation are only asking for
the AED 1,000,000.00. They are
only asking for a refund, not
compensation of expectation
interest or specific
performance. Then why are
developers clutching at force
majeure as if it is going to
save them from refunding that
amount? Consideration must move
from both parties. If there has
been a failure of consideration
from one side, the truth is that
no system of law and no legal
principle allows any party to
keep money belonging to another
party without giving anything in
exchange, unless that money was
given as a gratuitous gift. |
| |
|
|
|
|
 |
|
 |
|
|
|
Fareya
Azfar
Partner
|
|
Dubai,
UAE
Tel:
+971 4
4477044
Fax:
+971 4
4477088
Email:
fareya@tlg.ae |
|
|
|
|
|